Capital Projects
Name/Description | Water or Sewer | Status | Design Year | Bid Date and results | Bid Information | awarded | Estimated Cost | Estimated Start/completion dates |
---|---|---|---|---|---|---|---|---|
Wooden Shoe & Shafor Rd - Replace approximately 10,314' of 6" and 8" water main and appurtenances. | Water | Bidding | 2020 | 8/17/2021 |
Tim McQueen (513) 785-5168 |
Ford Development | $2,591,690 | Fall 2021/Summer 2022 |
Pheasant Hills/Bardean Water Main Replacement - Replace approximately 3,886' of 6" water main and appurtenances. | Water | Planning/Design | 2018/2019 | TBD |
Tim McQueen (513) 785-5168 |
TBD | $407,420 | Spring/Winter 2022 |
Port Union LeSaint Sanitary Sewer Rehab | Sewer | Construction | 2021 | 2/23/2021 |
Constance Kepner |
TBD | $624,380 | Early 2021 |
Maud Area Water Main Replacement - Replace approximately 3,612' of 10" and 6,125' of 6" water main and appurtenances. | Water | Planning/Design | 2021 | TBD |
Tim McQueen |
TBD | $1,363,180 | Summer 2022/Spring 2023 |
Gano Rd., Sewer Lining Project - Install 1,874' of CIPP sewer lining and grout existing mains | Sewer | Bidding | 2021 | 10/13/2021 |
Tim McQueen |
TBD | $187,000 | Spring 2022 |
West Chester Rd., 6" Water Main Extension - Install 1,579' of 6" water main and appurtenances. | Water | Construction | 2021 | 09/02/2021 West Chester Twp. |
Tim McQueen |
JNT Excavating | TBD | Fall 2021/Spring 2022 |
Five Points Sanitary Sewer Replacement - Install 275' of 18", 15" and 12" PVC sewer main and appurtenances. | Sewer | Bidding | 2021 | 10/15/2021 |
Jeff Frechtling |
TBD | $307,000 | Winter 2021/Spring 2022 |
Van Gordon and Voice of America Elevated Storage Tank Refurbishment | Water | Bidding | 2021 | 10/15/2021 |
Jack Thornsberry |
TBD | $583,000 | Winter/Summer 2022 |
Netherland Dutchland Blvd. Area Water Main Replacement - Replace approximately 6,280' of 6" and 8" water main and appurtances. | Water | Design | 2022 | TBD |
Tim McQueen |
TBD | TBD | Fall 2023/Spring 2024 |
LIFT STATIONS | ||||||||